一、编制依据 ···················································································································· 2 二、临建设施总体规划方案 ······························································································ 2 1、办公区、生活区场地布置 ································································································ 2 2、生活区平面布置 ··············································································································· 6 3、施工生产区场地布置 ········································································································ 6 4、试验室、值班室、工具房 ································································································ 8 5、临时用水 ·························································································································· 8 6、临时用电 ·························································································································· 9 7、排水、排污 ······················································································································ 9 8、消防设施布置 ··················································································································· 9 9、临边防护 ·························································································································· 9 10、班前讲台 ······················································································································· 10 三、安全文明管理措施 ···································································································· 11 1、办公、生活区管理措施 ··································································································· 11 2、现场管理措施 ·················································································································· 12 3、工地卫生 ························································································································· 15 4、保障措施 ························································································································· 15 四、附图 ························································································································· 15
1
天津地铁6号线工程土建施工第R3合同段左江道站
及梅江风景区站临建施工方案
一、编制依据
1、天津市地铁6号线R3标招标文件中文明施工要求; 2、天津地铁建设工程文明施工标准化图集;
3、国家、天津市现行的有关建筑工程文明施工标准化工地相关规定; 4、申请提供的用水、电接口位置;
5、我单位类似工程施工经验及设备物资资源;
二、临建设施总体规划方案
场地布置结合本标段施工总体组织安排设置,本项目施工场地布置实行办公生活区和施工生产区分开布置。根据现场条件及交通导行要求,计划分三期进行,一期施工围护结构,二期施工车站主体,三期施工附属结构。
1、办公区、生活区场地布置
左江道站办公区、生活区统一设置在友谊南路东侧绿化带内。项目部13间,工人生活区33间。梅江风景区站办公区、生活区统一设置在友谊南路西侧绿化带内,宿舍24间,其他用房18间。房屋采用双层夹岩棉防火材料的豪华型活动板房,红色屋顶,活动板房大样见图1。
图1 活动板房示意图
⑴ 活动板房
2
板房基础均采用200mm×200mm的C20素砼地基梁,砼采用商品砼。墙板基础梁范围以内浇筑100mm厚C20砼垫层,垫层上铺贴5mm厚600mm×600mm光面地板砖;厕所及浴室屋内地面铺贴300mm×300mm防滑地砖;所有房屋顶棚均采用5mm厚600mm×600mm乳白色压花石膏板吊顶。项目部内外露场地采用100mm厚C20素砼硬化。
⑵ 各区大门
左江道站办公区大门采用5m宽平开大门,两侧门柱高3m,边长0.8m×0.8m;左江道站施工区及梅江风景区大门宽10m,大门两侧门柱高3m,边长1m×1m,镶贴蘑菇灰瓷砖,柱顶装照明景观灯。
图2大门示意图
⑶ 区域卫生
在办公区设环保型垃圾桶,可回收物品与不可回收物品分开放置,生活垃圾集中处理,派专门的保洁人员每天收集垃圾,并打扫办公区及室外的卫生。见图3
图3垃圾桶示意图
3
⑷ 现场卫生
在施工区域设分类垃圾回收池,见图4
图4垃圾桶示意图
⑸旗台
梅江风景区项目部(主项目部)院内设一座旗台,采用砖砌基座,外贴褐红色或黑色大理石面,有金黄色企徽和企业名称。旗杆为不锈钢材料,国旗旗杆高11m。旗台效果见图
5。
图5 旗台示意图
⑹会议室布置
主项目部会议室采用4间活动板房,会议室布置讲求美观、大方、实用,能容纳40人
4
开会以及满足职工安全教育培训等功能要求,会议室效果见图6。
图6 会议室效果图
⑺办公区场地
主项目部院内修建半幅篮球场,其周边设若干花坛,其余场地全部采用100mm厚C20素砼硬化。
⑻ 五牌一图
左江道站施工区南侧、梅江风景区站施工区南侧分别布置“五牌一图”,采用不锈钢结构边框,外侧玻璃保护。效果见图7。
图7 五牌一图效果图
5
2、生活区平面布置 ⑴ 晾衣区
晾衣区内设置晾衣架,采用φ30mm不锈钢管架立焊接,高度2m,顶部搭设PVC透明雨棚。
⑵ 化粪池
在两个车站生活办公区各设一个化粪池,所有生活污水通过化粪池处理以后再排入市政污水管网,化粪池定期进行抽排。化粪池长4.8m,宽2.5m,高2.5m。
⑶ 供暖与制冷
办公区取暖采用冷暖两用空调,每个房间一台,空调设独立供电线路。 ⑷ 卫生间及浴室
卫生间与浴室地面均采用防滑地板砖铺设,内墙面采用釉面砖镶贴,顶棚采用防水吊顶,浴室采用淋雨喷头,卫生间和浴室均用夹心板隔离。
⑸ 食堂、餐厅
项目部食堂和工人食堂分别设置在各自的区域,地面铺设500mm×500mm地板砖,天花采用5mm厚600mm×600mm乳白色压花石膏板吊顶。厨房地面铺设300mm×300mm防滑地板砖,厨房需设单独的煤气罐间。
3、施工生产区场地布置
两个地铁站的施工,均分为围护结构、车站主体、附属结构三个阶段施工。 ⑴ 围挡
施工围挡分为临时围挡和永久围挡,外圈围挡采用砖砌永久围挡,高度2.5m,外层贴瓷砖。如图8所示。
图8 永久围挡示意图
6
左江道站生活区项目部与民工生活区之间设临时围挡分隔,临时围挡采用压型彩钢板护栏,护栏高度2.2m。
左江道站施工区域西侧设置声屏障以防止扰民(详见声屏障施工方案)。 ⑵ 大门、冲车设备
在左江道站及梅江风景区站南北端各设置一个大门,大门宽度10m,为双开门,门扇采用5mm厚铁皮和L30角钢骨架加工而成,高度为2.2m。大门两侧门柱高3m,边长1m×1m,外贴灰色蘑菇石瓷砖。
大门内设置自动洗轮机,如图9所示
图9 自动洗轮机示意图
⑶ 场地硬化及施工便道
生活办公区域场地采用100mm厚C20混凝土硬化。左江道站施工区域(包括地连墙范围内)采用20cm厚单层钢筋网混凝土,履带吊行走路线区域采用30cm厚Φ16@200mm双层双向钢筋网C30混凝土。
⑷ 钢筋加工场
每个车站围护结构施工均设置一个钢筋加工场,其中左江道站钢筋加工场位于地连墙范围内,梅江风景区站钢筋加工场位于地连墙西侧;每个钢筋加工场各设置一套钢筋加工机械(包括钢筋切断机、钢筋弯曲机、闪光对焊机、钢筋直螺纹套丝机)。
二期结构施工期间设置钢筋加工棚,钢筋加工在钢筋加工棚内进行。如图10所示
7
图10钢筋加工棚
⑸ 泥浆循环系统
两个车站泥浆循环系统在南、北两端各配置一套,全采用移动泥浆箱组成,按地连墙施工高峰期每天成槽4幅确定泥浆罐储量。如图11所示。
图11泥浆循环系统示意图
⑹ 临时堆土场
地连墙土方不能直接外运,因此在各站施工场地内分别设置一个临时堆土场。堆土场设在地连墙范围内,位置根据地连墙施工进展调整。
4、试验室、值班室、工具房
试验室、值班室、门卫等采用彩钢板房整体搭建而成,房间内地面为50mm厚砂浆抹面压光。
5、临时用水
各站施工时,从城市自来水管网上各接一根DN100水管作为项目临时用水主管。进入房间的分水管采用DN50mm水管,用水集中区域每隔一定间距设一闸阀,水管布设,线路
8
顺直、规范,水管埋入地下50cm。
6、临时用电
两地铁站各设2台400KVA变压器,经项目部一级配电柜后引至各施工用电点。具体另见临电施工组织设计。
7、排水、排污
工地雨水通过雨水井(污水通过化粪池沉淀)最终排入城市排水管网。排水、排污应提前与城市雨污水管理单位沟通,办理相关手续后再排放。
8、消防设施布置
在各生产和生活场地按规定配备足够的消火栓及灭火器。同时与当地消防部门联系,取得市政部门的检查认可,并做好自检工作,确保设施随时处于良。如图13所示。
图13 消防设施示意图
9、临边防护
基坑边围挡采用定型钢栏杆,围挡高1.2m,立柱间距2m。围栏设于地连墙外侧导墙顶部,围栏立柱插入导墙顶部预埋套管内,围栏下侧做100mm高钢板挡水线,防止路面雨水及杂物落入基坑内。基坑边围挡示意图如图14所示。
9
图14 临边防护示意图
10、班前讲台
班前讲台采用砖砌抹砂浆,或者用光洁的木板搭设,长4m、宽2m,角部做圆弧处理,讲台高于地面150mm;上部用角钢焊接成门柱,横梁,外包薄铁皮,如图15所示:
图15 班前讲台示意图 10
三、安全文明管理措施
1、办公、生活区管理措施 ⑴ 宿舍:
A.统一设置床铺和储物柜,严禁使用通铺,每间不超过8人,布置合理,卫生清洁,室内通风照明良好、整洁。
B.用电无私拉乱接情况,有保暖、消暑、防蚊虫叮咬措施。
C.宿舍内应设置垃圾桶,生活区室外提供员晾晒衣物的场地,并悬挂标识牌。 D.各生活区统一设置低压手机充电柜,如图16所示。
图16 手机充电示意图
⑵ 食堂:
A.食堂设置应符合食品卫生法规的要求,并取得卫生行政主管部门发放的卫生许可证,炊事员定期体检,持健康证上岗,职工膳食、饮水供应等应符合卫生要求,配备必要的排风设施和冷藏设施。
B.食堂的燃气罐应单独设置存放间,存放间应通风良好并严禁存放其他物品,食堂外应设置密闭式泔水桶,并应及时清运。
C.悬挂食堂管理办法和卫生要求,尺寸为0.6m×0.8m,参照标识标牌制作。 ⑶ 卫生间:
11
A.结构要稳定、牢固、防雨、防风,新建厕所地板采用混凝土浇注并铺设地板砖,大小便池配有自动冲水系统。
B.严格采用水冲式,可悬挂一些“节约用水”的标识,实行专人管理、及时清扫,及时消毒、防止蚊蝇孳生、保持卫生、保障正常使用。
⑷ 配电箱管线布置:
a.配电箱统一安装漏电保护器,挂“当心触电”、“有电、危险”警告牌。b.各用电设备采用开关箱,做到“一机、一闸、一漏、一箱”。
2、现场管理措施
① 在工地的主要出入口显要的位置设置五牌一图(工程概况、管理人员名单及监督电话、安全生产、文明施工、消防保卫五板;施工现场总平面图),标志牌在整个施工期间保护完好、醒目,并在竣工后拆除。如图17所示。
图17 五牌一图示意图
② 工程材料、构件分类堆放、排列整齐;机具设备定机定人保养,保持运行整洁,机容正常。如图18所示。
12
图18 材料及加工区整齐布置
④ 施工现场合理设置出入口,用砼进行硬化,出入口设置符合标准和规范的运输车辆冲洗和排水设备。施工道路出入口和交叉口设置交通指令标志,夜间设置示警灯及照明灯,保证车辆和行人的安全,暴雨季节安排专人值班。照明灯具如图19所示。
图19 照明灯示意图
⑤ 加强土、石方施工管理,挖出的湿土先卸在场内暂堆,滤干后再转运外弃,防止湿土与泥浆沿途滴漏污染公路。运输车辆驶出施工现场前,冲洗干净,不带泥出场。
⑤ 处理施工碴土,办理有关审批手续,按照规定的数量、运输线路、时间、倾倒地点进行处置。
⑥ 施工现场人员挂牌,持证上岗;炊事员有健康合格证;施工人员穿戴统一的工作服。施工现场坚持日做日清,工完场清,严禁乱堆乱放建筑垃圾。
⑦ 健全各项文明施工的管理制度,如岗位责任制、经济责任制、奖罚制度、会议制度、专业管理制度、检查制度、资料管理制度等。如图20所示。
13
图20 现场管理制度示意图
⑧ 做到“两个同步”,实行“三个结合”。即文明施工方案和施工方案同步设计、同步审查。工程质量、安全检查和文明施工检查相结合;监督检查与奖罚制度相结合;项目部自查与抽查、工区互检相结合。
⑨ 按照天津有关政府部门和业主针对地铁工程制定的有关文明施工的规定的要求执行,同时无条件遵守针对地铁工程施工方面的其它临时规定。
⑩ 施工用电应符合TN-S接零保护、三级配电、三级漏电保护和动照分设原则。电箱要放置规范整齐。如图21所示。
图21 配电箱示意图
14
3、工地卫生
① 管理区设置醒目的环境卫生宣传标牌和责任区包干图。现场“五小”设施齐全、设置合理。
② 管理区内防止蚊蝇滋生,同时要落实各项除四害措施,控制四害滋生。管理区内做到排水畅通,无污水外流或堵塞排水沟现象。在施工现场尽可能创造条件进行绿化布置。
③ 办公区、生活区、施工便道、厕所等经常打扫,洒水控制扬尘,保持现场整齐清洁。 如图22所示。
图22 现场洒水降尘示意图
4、保障措施
① 随时接受地方政府的监督和建设单位的定期检查,对存在的问题及时进行整改,切实搞好文明施工。
② 项目部成立信访办,定期走访施工现场周围居民,妥善解决居民投诉。
③ 接受建设管理方和监理对工地文明施工情况的检查、整改。督促工区加强自查,班组和个人进行自查和互检。对查出的问题,及时发出整改单。根据检查结果汇总、评比,考核出评比总分。
④ 文明施工管理小组依照“文明施工评分标准”规章制度,在工程建设中途及末尾进行总结和考核,结合文明班组、文明职工的评比进行考核,并将平时检查情况同奖金发放结合起来。
四、附图
15
2
1
2
会议室大门 洗漱男洗浴女厕洗浴大门男厕花坛停车位停车位停车位停车位女厕彩板围挡女洗浴茶炉厨房厨房厨房厨房宿舍宿舍宿舍男厕宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍监理宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍宿舍门卫厨房餐厅施工技安全环副经理术部保部左江道临建二层平面布置图高砖砌围墙宿舍民工生活区宿舍
3
2.3男洗浴男厕女洗女厕浴综合茶炉保障部花坛花坛会议室宿舍宿舍宿舍宿舍宿舍宿舍宿舍活动室监控室总工宿舍宿舍门卫信访办经理旗台半篮球场阅读室财务餐厅副经理花坛花坛厨房副经理贵宾室安环部施技部业主监理经营部项目部二层平面布置图监理小餐厅高砖砌围墙宿舍宿舍宿舍宿舍宿舍宿舍宿舍
4
5